The contractor called tonight. He has another job at the beginning of the week. Should it take longer than expected, he will be at our place Thursday morning. Otherwise, it will be Wednesday. This gives us a little more time to get our end done. If things go well and we finish early, we can then get started on changing out the upstairs window.
They will, however, be delivering the septic tanks on Monday. Two tanks, 8' long by 52" wide. We're going to have to find a spot to put them that won't interfere with our getting the bulldozer out and to the clearing.
While we are going to reimburse our account for the difference between what we had saved already for the woodstove and what it actually cost, that will take some time. We should have enough left to pay for the septic. We're hoping there'll even be a little left over. Keeping fingers crossed.